Advantage told Place North West that 1,700 cubic meters of timber frame had been used and lauded the building as having the largest timber content of any on-site project in Europe.
The whole of the residential home was burnt down in 2019 due to the materials used and defective cavity walls.
Missing cavity barriers and fire-stopping can’t be retrofitted to a large modular building? Not without almost destroying the whole building.
If the cavity barriers are imperfect or not installed, the entire building is capable of spreading internal fires out to the exterior envelop where it may spread, and vice versa
Size3 FloorsCost £240KPrintevacstac.co.uk